News
Thứ 6, Ngày 28/10/2022, 09:00
Removing difficulties and obstacles to speed up the clearance of National Highway 13
Cỡ chữ: Font size: Giảm (A-) Mặc định (A) Tăng (A+)
28/10/2022

​PORTAL - On the afternoon of October 27, the Steering group for implementing BOT project to upgrade and expand National Highway 13 (NH13), led by Mr. Nguyen Hoang Thao – Permanent Deputy Secretary of the Provincial Party Committee, Head of the Steering Group inspect the site and work directly with the locality on the progress of compensation and site clearance for the project to upgrade and expand National Highway 13, section in Thu Dau Mot city and Thuan An city. Accompanying was Ms. Nguyen Truong Nhat Phuong - Vice Chairman of the Provincial People's Council, leader representatives of provincial departments, committees and branches.

​Reporting on the compensation implementation of NH13 site clearance projects, the People's Committees of Thu Dau Mot City and Thuan An City said that the NH13 site clearance project (section from Tu Do intersection to Le Hong Phong crossroads) in Thu Dau Mot city and Thuan An city has 132 cases, of which 128 cases (106 households and 23 organizations) belong to Thuan An city and 27 cases (26 households and 01 organization) belong to Thu Dau Mot city. Up to now, the site clearance has reached 90%, the goal is to complete all the remaining volume in November 2022 and hand over the site of the project in December 2022. The site clearance project from Ong Bo Bridge to Huu Nghi intersection has 102 cases (91 households, 11 organizations and enterprises within the scope of clearance). Thuan An City People's Committee has issued a notice of land acquisition in 101/102 cases. Currently waiting for the approval of the unit price to take the next steps to ensure that the disbursement in the fourth quarter reaches 95% of the total project compensation estimate. The site clearance project from Vinh Phu welcome gate to Ong Bo Bridge has a total of 255 households and 42 organizations affected, and is carrying out inventory of assets, appraisal of plan for survey, measurement, tally and notice of land acquisition. After the compensation unit price is approved, in December 2022, about 20-30% of the total project compensation estimate will be paid.

​ 

Provincial leaders survey the actual project construction and site clearance from Le Hong Phong crossroads to Huu Nghi intersection

 

Workers are constructing the work

​ 

Upgrading and expanding NH13, section from Vinh Phu welcome gate to Le Hong Phong Street to 8 lanes

To ensure the project schedule, the People's Committees of Thu Dau Mot City and Thuan An City suggested that the province soon approve the compensation price plan for cases in the section from Vinh Phu welcome gate to Huu Nghi intersection so that the localities can propagate and pay compensation to the people. At the same time, paying attention to the arrangement of land fund to implement resettlement areas for households having their houses and land cleared. The localities also proposed the establishment of a propaganda and advocacy group to create consensus among the people.

​ 

 Overview of the meeting with Thu Dau Mot City and Thuan An City

 

Representative of departments and branches speaks at the meeting

After actually surveying the section from Le Hong Phong crossroads to Tu Do intersection and listening to reports from localities, Mr. Nguyen Hoang Thao shared the difficulties and obstacles that the localities are facing in the implementation of site clearance. At the same time, he suggested that departments, branches and localities review all stages to remove difficulties and obstacles, contributing to speeding up the progress of site clearance; calculate compensation prices that are reasonable and beneficial to the people. For households having their houses and land cleared, the locality needs to arrange resettlement areas to ensure quality to serve the living and business needs of the people. The site clearance must be carried out according to the rolling and synchronous plan. The Permanent Deputy Secretary of the Provincial Party Committee suggested that the Provincial People's Council and the Department of Justice continue to study the provisions of the law and issue documents to create a legal basis for the project to be implemented on schedule.

 

Permanent Deputy Secretary of the Provincial Party Committee Nguyen Hoang Thao speaks at the meeting

​Reported by Mai Xuan- Translated by Thanh Tam

Lượt người xem:  Views:   721
Chia sẻ:
Share:
Others
 
 
Manage PermissionsManage Permissions
|
Version HistoryVersion History

Tiêu đề

Hình ảnh

Hình ảnh mô tả

Tóm tắt

Nội dung

Link thay thế nội dung

Ngày xuất bản

Tin nổi bật(Time)

Tác giả

Số Trang

Số Ảnh

Số tiền

Trạng thái

Lịch sử

Số lượt người đọc

Phân loại

Loại bài viết

Audio

Tin liên quan

Từ khóa

Email

Hệ số ảnh

Hệ số lương cơ sở

Hệ số tin

LuongCoSo

Tiền nhuận bút

Tin nổi bật

Approval Status

Attachments

Content Type: Tin Tức Mở Rộng
Version:
Created at by
Last modified at by
News