According to the report, the Bac Tan Uyen - Phu Giao - Bau Bang Road Project has a length of nearly 48 kilometers, with a total investment cost of more than 3,800 billion VND, passing through the districts of Bac Tan Uyen, Phu Giao, and Bau Bang. In particular, the Road Construction Project from Tan Thanh to Tam Lap Bridge is invested by the People's Committee of Bac Tan Uyen District (length about 9.32 kilometers). Up to now, the project has been basically completed, the investor is implementing procedures to carry out acceptance and put the project into use.
Provincial Party Secretary Nguyen Van Loi listens to Phu Giao district leaders report on project construction schedule
Road Construction Project from Tam Lap Bridge to Dong Phu is invested by Phu Giao District People's Committee (length about 12.15 kilometers). To date, construction schedule has reached about 44.7%. According to the contract, it is expected to be completed in April 2024. Road Construction Project from Tam Lap Junction to Bau Bang is invested by Phu Giao District People's Committee (length about 17.79 kilometers). Construction schedule to date has reached about 76.8%, on schedule set out. About 92.1% of the site has been handed over.
The Tan Long - Lai Uyen road construction project invested by the People's Committee of Bau Bang district (length about 8.65 kilometers) has completed over 90% of phase 1, the district is implementing phase 2.
This is one of the projects considered important in creating motivation for the development of the Southeast Region in general. Once completed and put into use, the project will shorten travel time and reduce the cost of transporting goods to important traffic hubs in Dong Nai province, Ba Ria - Vung Tau and Ho Chi Minh City, creating momentum for the development of Binh Duong province and the 3 districts where the road passes through.
The project implementation is facing difficulties in the section through Phu Giao district due to site clearance
However, project implementation is facing difficulties in the section through Phu Giao district due to site clearance (length of about 1,800 meters), 53 medium and low voltage electric poles and 01 high voltage electric pole, 1,170 meters of clean water pipes running along both sides of the road have not been relocated.
Faced with the above situation, the construction unit recommended that the investor urgently relocate the electricity and clean water systems and hand over the construction site according to regulations.
Provincial Party Secretary Nguyen Van Loi speaks at the inspection
Through the opinions of the units, Provincial Party Secretary Nguyen Van Loi requested Phu Giao district to coordinate closely with relevant parties to promptly remove difficulties and obstacles and speed up schedule to put the road into use to promote the effectiveness of the project. The construction unit needs to mobilize maximum forces and means to shorten construction time but must ensure project quality and urgently complete the project by the end of 2023. Phu Giao district must mobilize people to agree to hand over the remaining land to the construction unit to implement the project; at the same time, research to maximize the use of policies to benefit the people. Regarding resettlement, the district needs to consider suitable locations to arrange resettlement for people. Speeding up the relocation of electricity and water systems on the road to keep construction on schedule.
Provincial Party Secretary Nguyen Van Loi discusses with the project construction unit