PORTAL - That is the guiding opinion of Provincial Party Secretary Nguyen Van Loi at the survey and inspection of the progress of social housing construction at the Chanh My ecological urban area project in Chanh My ward, Thu Dau Mot City on the afternoon of April 22.


​Chanh My Ecological Urban Area project is invested by the Housing and Urban Development Holdings Corporation Limited (HUD), with a scale of more than 340 hectares. To date, the project has disbursed investment capital of more than 2,070 billion VND.

 

The Social Welfare Housing Project is being implemented on schedule

Located in the Chanh My Ecological Urban Area project, the social welfare housing project has an area of more than 27 hectares, including 06 12-story apartment buildings with 978 apartments, and an area of 38.5 m2 to 63.5 m2. After completing procedures for publicizing social housing product information, HUD has received about 1,200 registration dossiers wishing to purchase and has reviewed eligible subjects according to current regulations and submitted them to the Binh Duong Department of Construction for appraisal. The project implementation progress is expected to complete acceptance and put into use 03 towers phase 1 with 456 apartments in the third quarter of 2025.

 

Mr. Ta Dung - Deputy General Director of HUD states difficulties and problems related to project implementation

Reporting to the Delegation, Mr. Ta Dung - Deputy General Director of HUD stated difficulties and problems related to project implementation. For example, some regulations on conditions for social housing support policies are inappropriate, leading to people in need not receiving access to products; the handover of the site is still facing difficulties, affecting the project progress, etc.

 


 

Leaders of departments and branches present solutions to remove difficulties and obstacles in project implementation

Through the opinions of units and localities, Provincial Party Secretary Nguyen Van Loi understood the difficulties of the investors during project implementation and highly appreciated the progress of the project, which has now basically completed all legal procedures. Regarding site clearance, the Secretary said that there were not many households that have not yet cleared and reclaimed their land, so he requested localities to continue to propagate, mobilize, and explain to people the benefits of the project in the overall development of the province, and apply policies to compensate, resettlement, and ensure the rights of people in the cleared area.

 

Provincial Party Secretary Nguyen Van Loi speaks at the meeting

The Secretary requested the Trade Union levels to reach workers who need to buy social housing and act as a bridge to help them access and buy social housing, ensuring the appropriate people. Relevant departments and branches must work with the investor to remove difficulties and obstacles so that the project can be completed soon and operate effectively.

 

Provincial Party Secretary Nguyen Van Loi discusses with the investor of the social housing project in Chanh My Ecological Urban Area

 

Provincial leaders take a group photo with HUD leaders at the Welfare Housing Area

Lượt người xem:  Views:   231
Chia sẻ:
Share:
Others
 
 
Manage PermissionsManage Permissions
|
Version HistoryVersion History

Tiêu đề

Hình ảnh

Hình ảnh mô tả

Tóm tắt

Nội dung

Link thay thế nội dung

Ngày xuất bản

Tin nổi bật(Time)

Tác giả

Số Trang

Số Ảnh

Số tiền

Trạng thái

Lịch sử

Số lượt người đọc

Phân loại

Loại bài viết

Audio

Tin liên quan

Từ khóa

Email

Hệ số ảnh

Hệ số lương cơ sở

Hệ số tin

LuongCoSo

Tiền nhuận bút

Tin nổi bật

Approval Status

Attachments

Content Type: Tin Tức Mở Rộng
Version:
Created at by
Last modified at by
News