Joining him were Mr. Mai Hung Dung - Standing Vice Chairman of the Provincial People's Committee (PPC), leaders of departments and branches, and Tan Uyen City.
The Bach Dang 2 bridge is 945.81m long. Its starting point coincides with the ending point of the project to build a road leading to the bridge on the Binh Duong side, the ending point intersects with the Huong Lo 7 route on the Dong Nai side.
This construction started on December 20, 2021. To date, the implementation volume has reached 70% of the contract.
Regarding site clearance compensation, the Tan Uyen City People's Committee has approved a compensation plan for 14 households with a total estimate of 44,124 billion VND. To date, the handover of premises has reached 58%, and in February 2024, the remaining cases that have received money will continue to be handed over.
The construction unit is accelerating the project's progress and implementing the construction of the remaining items. It is expected to complete the bridge segments in early June 2024 and complete the project in the third quarter of 2024.
The Provincial Leaders listen to a report on the Bach Dang 2 bridge project's progress.
The Provincial Leaders monitor the Bach Dang 2 bridge project's progress.
Through monitoring the project, the Provincial Party Committee Secretary Nguyen Van Loi highly appreciated and praised the working spirit of the construction unit and the construction progress of the Bach Dang 2 bridge. The Secretary emphasized that this project connects Binh Duong province with Dong Nai province which is important in connecting the region. Binh Duong will continue to build more projects connecting to Long Thanh Airport. Therefore, the localities of Tan Uyen and Bac Tan Uyen must do a proper job of site clearance and mobilize people to hand over the site for construction projects.
The Provincial Party Committee Nguyen Van Loi directs the monitor meeting.
On this occasion, the Provincial Party Committee presented Tet gifts to workers who are working on the Bach Dang 2 bridge project. He also encouraged them to continue working hard to ensure the project's progress.
The Provincial Party Committee Nguyen Van Loi presents gifts to the workers at the Bach Dang 2 bridge project.
The Standing Vice Chairman of the PPC presents gifts to the workers at the Bach Dang 2 bridge project.
The Provincial Leaders take a group photo with the Bach Dang 2 bridge construction unit.