Do compensation and site clearance well to speed up the implementation process of key projects
Cỡ chữ: Font size: Giảm (A-) Mặc định (A) Tăng (A+)
18/09/2020 | Nguyen Trang
​PORTAL - In the morning of September 16, at Binh Duong Administrative Center, the Standing Committee of the Provincial People's Council supervised the implementation of some key public investment projects in the province. Mr. Ho Quang Diep - Member of Provincial Standing Committee, Standing Vice Chairman of Provincial People's Council chaired the monitoring session.

The participants included Mr. Nguyen Thanh Truc - Vice Chairman of the Provincial People's Committee and leaders of departments, agencies, branches, districts, towns and cities.

At the monitoring session, delegates listened to the Provincial People's Committee reporting on the implementation of public investment capital plan of key public investment projects and works in 2018, 2019 and the first 5 months of 2020. Accordingly, the total implemention volume in 2018 is 2,574 billion 692 million Vietnam dong, reaching 79.7% of the plan, the disbursement value as of January 31, 2019 is 2,417 billion 463 million Vietnam dong, reaching 74.8% of the plan. In 2019, the total implementation volume is 2,416 billion 397 million Vietnam dong, reaching 40.7% of the plan, the disbursement value as of January 31, 2020 is 2,885 billion 479 million Vietnam dong, reaching 48.5% of the plan.

Some projects with large capital but low disbursement compared to the plan such as: The project of compensation for the extended My Phuoc - Tan Van road, site clearance of the My Phuoc - Bau Bang road for development, site clearance of upgrading and expanding DT.743 road from Ong Cu temple to Song Than intersection, Bung Biep- Suoi Cat drainage, Di An drainage system - Tan Dong Hiep industrial park (29.7%), building an embankment against Dong Nai river erosion from Rach Tre bridge to Tan Uyen Party Committee - Phase 2, improving the water environment of the South of Binh Duong in phase 2 ...

Particularly in 2020, the plan to allocate capital for 41 key projects with a total capital of 6,021 billion 979 million VND, accounting for 44.7% of the provincial capital plan. As of May 31, 2020, 600 billion 203 million VND was disbursed, reaching 10% of the plan. It is expected that in the third quarter of 2020, Binh Duong will invite bids and start a number of new projects such as: Construction of North-South Road No.3, Project of improving the water environment of the South of Binh Duong in phase 2, the road from Tan Thanh to Tam Lap bridge (Tan Dinh commune) belongs to the North Tan Uyen - Phu Giao - Bau Bang route for development, Bach Dang 2 bridge which is over Dong Nai river; roads and bridges connecting Binh Duong and Tay Ninh province etc.


The supervisory team of the Provincial People's Council supervises implementation of the 1,500-bed hospital project

Discussing at the meeting, members of the supervisory team analyzed and introduced limitations in disbursement such as: Most of the key projects were financed with a lot of capital but the progress of implementation was slow; time of compensation and site clearance is prolonged ... Thereby, leaders of the provincial People's Committee and departments, agencies, branches and localities have explained and clarified the causes and problems in the process of implementing some projects, investment preparation, project implementation, site clearance and implementation of key projects to celebrate the 11th Provincial Party Congress ...

At conclusion of the meeting, Mr. Ho Quang Diep showed his understanding of the difficulties, problems and pressures in the process of implementing key projects in the province. Assessing the main cause of the delay in disbursement of public investment capital is due to problems in compensation and site clearance, the Standing Vice Chairman of the Provincial People's Council proposed the Provincial People's Committee to direct units and localities to do this work well. Besides, enhancing the responsibilities of the leaders, strengthening the coordination among units, localities, among investors, construction units and beneficiaries; selecting qualified consulting, supervising and construction units; carrying out synchronous implementation of bidding packages in the same project etc. In the long term, it is necessary to create a "clean" land fund to implement works and projects in order to limit problems in compensation and site clearance.

Lượt người xem:  Views:   879
Chia sẻ:
Share:
Others
 
 
Manage PermissionsManage Permissions
|
Version HistoryVersion History

Tiêu đề

Hình ảnh

Hình ảnh mô tả

Tóm tắt

Nội dung

Link thay thế nội dung

Ngày xuất bản

Tin nổi bật(Time)

Tác giả

Số Trang

Số Ảnh

Số tiền

Trạng thái

Lịch sử

Số lượt người đọc

Phân loại

Loại bài viết

Audio

Tin liên quan

Từ khóa

Email

Hệ số ảnh

Hệ số lương cơ sở

Hệ số tin

LuongCoSo

Tiền nhuận bút

Tin nổi bật

Approval Status

Attachments

Content Type: Tin Tức Mở Rộng
Version:
Created at by
Last modified at by
News